On June 6, 2019 Hydrocarbon Well Service checked cement on 10 3/4” casing on the Odnr well, spot rig back over well, rigged up drill collars, power swivel, hydraulic unit, ran hydraulic hoses and kelly hoses to begin drilling, hooked hoses to pit for returns, got pumps primed, and pumped 200 bbl water in tanks.

On June 6, 2019 Hydrocarbon Well Service checked TOC in the Eqt well @ 1610′. Ran spear inside 6 1/4” and worked casing with no movement, ran bond log inside casing and bond showed that casing was 100% bonded to surface.
On June 6, 2019 a representative from Hydrocarbon Well Service met with Tribune Resources to look at 4 wells to bid on.