Hydrocarbon Well Service – Daily Update 4/22/21

Hydrocarbon Rig 9 Crew continued milling with tapper mill. Tripped out and inspected mill, decision was made to get tripped back in with work string and set cement plug tomorrow.

Hydrocarbon Rig 12 Crew finished reclamation, walked next site and started mob of equipment.

Hydrocarbon Rig 14 Crew set up equipment on site, and got rig rigged up.

Hydrocarbon Roustabout Crew set tank for Big Sand Drilling.

Rig 9 Site

 

Rig 12 Reclamation

 

Rig 14 Site

 

Roustabout Crew