On June 6, 2019 Hydrocarbon Well Service checked cement on 10 3/4'' casing on the Odnr well, spot rig back over well, rigged up drill collars, power swivel, hydraulic unit, ran hydraulic hoses and kelly hoses to begin drilling, hooked hoses to pit for returns, got pumps primed, and pumped 200 bbl water in tanks.
Field Updates · June 13, 2019
Hydrocarbon Well Plugging Report 6/6/2019
On June 6, 2019 Hydrocarbon Well Service checked TOC in the Eqt well @ 1610'. Ran spear inside 6 1/4'' and worked casing with no movement, ran bond log inside casing and bond showed that casing was 100% bonded to surface.
On June 6, 2019 a representative from Hydrocarbon Well Service met with Tribune Resources to look at 4 wells to bid on.
More from the field

March 14, 2025
Plugging Abandoned Oil and Gas Wells in West Virginia: A Critical Effort for Environmental and Public Safety
West Virginia, rich in natural resources, has a long history of oil and gas production. However, thousands of abandoned and orphaned wells across the…

February 22, 2022
Hydrocarbon Well Plugging Experts 2/22/2022 - Well Plugging update
Hydrocarbon has been busy completing projects for the Ohio Department of Natural Resources and the West Virginia Department of Environmental Protection.…

January 29, 2022
Hydrocarbon Expert Well Plugging and Capping - 1/29/2022
Hydrocarbon Well Services, the premier oil and gas well plugging company has been very busy. We have been gearing up for opportunities surrounding our…