Hydrocarbon Well Services Daily Blog 5/21/2019

Hydrocarbon Well Services set a 200′ bottom hole plug on the Civil  Environmental Consultants well. Tripped out of hole (TOOH) with work string. Attempted pulling stretch again on 7″ casing with no movement in casing. Prep for wireline truck for in the morning.
Hydrocarbon Well Services set there surface plug in two stages on the Duquene Light Company’s well. Got cement back to surface, but dropping slowly. Will top off in the morning with cement and install monument and begin rig down.
Hydrocarbon Well Services set there surface plug on the Ohio Department of Natural Resources well. Got cement back to surface and pulled there 7″ casing. Cement was dropping in well, will top off in the morning and begin rig down.
Hydrocarbon Well Services mobilized equipment to Big Sand Drilling and began building dike around existing stock tank. Removed portion of next dike to swap out production tank.