Hydrocarbon Well Services Plugging Activity 4/15/19

Hydrocarbon Well Services ran bond log, ccl inside 3.5″ tubing and perforated below the packer on the Eqt well as directed by the inspector. Began tripping in work string to set bottom hole cement plug.
Ohio Department of Natural Resources: Hydrocarbon Well Services tagged cement plug top and began drilling out cement and open hole with 9 5/8″ tricone bit with power swivel.
Civil Environmental Consultants: Hydrocarbon completed site prep and began mobilizing equipment on site. Removed existing production equipment.