Hydrocarbon Well Services Plugging & Cementing Daily Blog 4/15/2019

Hydrocarbon Well Services finished tripping in 1.5″ work string and set a 192′ bottom hole cement plug on Eqt well, tripped out work string and set wireline truck up for Tuesday to shoot off 3.5″ tubing.
For the Ohio Department of Natural Resources, Hydrocarbon Well Services repacked the packing in the power swivel, and started back to drilling out hole. Target depth is 360′, then run 7″ casing in hole and cement in place.
Hydrocarbon Well Services could not get the the Civil Environmental Consultants well due to flooding, however they were able to begin removing production equipment off the second Civil Environmental Consultants well they are contracted to plug.