Hydrocarbon Well Service checked top of cement (TOC), shot 3.5″ tubing off at 2480′ and tripped 3.5″ tubing out of hole to set cement plug at tubing cut tomorrow.
Ohio Department of Natural Resources: Hydrocarbon Well Service continued drilling with 9 5/8″ tricone mill. At 70′ well began taking fluid. Mixed lost circulation material (LCM) and continued drilling and hauling 300 barrels (bbl) of water. Got drilled down 95′ and pulled back up inside 10 3/4″ casing. Will evaluate with inspector and engineer in the morning.
Hydrocarbon Well Service completed containment and rig up on the Civil Environmental Consultants well. Crew began pulling rods, and will complete tripping out rods and tubing tomorrow.